Follow the Rupee
Officer login
EN
हिंदी
मराठी
Home
Ward map
Wasted money
Next rupee
Contractors
Track a complaint
For citizens
What happened to my complaint?
Search
₹
BMC paid ₹78,683 while the road was under warranty
WO25-01572 · Ward R/C · The repair itself lasted 30+ days.
1
Complaint
10 Aug 2025
2
Assigned
12 Aug 2025
3
Work started
13 Aug 2025
!
Repaired (late)
15 Aug 2025
✓
30 days later
Contractor
Western Coast Asphalt Co
Cost
₹78,683
Took
4.8 days
On time?
No
📷
Citizen's photo
Nullah water overflowing onto road
🛠
Engineer's note
“Patched, needs resurfacing after monsoon” · Desilting and garbage removal
⚠ Audit flag:
Paid while under warranty
Ward report →
Or open a real story
✓
Fixed, and it lasted
Andheri East · खड्डा
↺
Fixed, then broke again
SV Road · खड्डे पुन्हा उखडले
…
Never fixed
Malad West · पानी भर गया
×2
Billed twice?
Powai · ₹1.7 lakh
3.1×
Billed far above the rate
Marve Road · ₹2.8 lakh
▦
A road patched again and again
SV Road · 170 repairs · ₹84.3 lakh · 38 broke again